Monday, November 21, 2011

Construction of this project is complete. All that remains is lift station start up procedures and punchlist.

Thursday, November 3, 2011

Next week, the contractor will be continuing punchlist work. Utility companies have completed their service connections to the lift stations and the contractor will be scheduling the lift station start up. Additionally, parkway restoration is scheduled to be completed around lift stations next week.

Friday, October 28, 2011

Next week, AT&T and Nicor will continue work on lift stations prior to the lift station start up. Also next week, the contractor will be installing asphalt surface course on Cariann Lane and will continue punch list repairs.

Wednesday, October 19, 2011

Starting next week, ComEd, AT&T and Nicor will be completing utility services to the lift stations prior to the lift station start up. Also next week, the contractor will be beginning punch list work.

Friday, October 14, 2011

Next week, the contractor will be beginning punchlist work. Additionally, ComEd, AT&T and Nicor will be completing utility services to the lift stations prior to the lift station start up within the next few weeks.

Wednesday, October 12, 2011

On the afternoon of October 12 the contractor will be coating the existing asphalt surface with fresh oil and sand on Arbor Lane. The oil will help the top coat of asphalt bond to the existing layer. The layer of sand is to help prevent tracking the oil into your driveways. Please try to keep your driving to a minimum while the oil dries. If you must drive on the oil, please drive slowly to help prevent splattering onto your vehicle.

Weathering permitting the contractor will then begin to pave the final layer of asphalt on Arbor Lane on Thursday, October 13.

Monday, October 10, 2011

UPDATE: Paving on Carriann Lane and Arbor Lane (between Glenview Road and Wilmette Avenue) is tentatively scheduled for Thursday of this week, weather permitting.

Friday, October 7, 2011

Next week, the contractor will be adjusting utility structures in preparation for asphalt paving on Carriann Lane and Arbor Lane (between Glenview Road and Wilmette Avenue). The contractor will also be working on parkway grading and restoration on Carriann Lane this week.

Friday, September 30, 2011

Next week, the electrical contractor is scheduled to continue wiring for the sanitary lift stations at Cariann Lane and Arbor Lane. On Cariann Lane, the concrete contractor is scheduled to begin installation of curb with the paving contractor scheduled to begin paving shortly after the curb installation.

Additionally, the paving contractor is scheduled to begin grinding the pavement on Arbor Lane in preparation for asphalt paving.

Friday, September 23, 2011

Next week, DiMeo Bros. is scheduled to continue piping within the sanitary lift station at Cariann Lane. Additionally, late next week the asphalt contractor will be grinding Arbor Lane from Glenview Road to Wilmette Avenue in preparation for asphalt resurfacing.

Friday, September 16, 2011

Next week, DiMeo Bros. is scheduled to continue work on the sanitary lift station at Cariann Lane.

Friday, September 9, 2011

Next week, DiMeo Bros. is scheduled to continue work on the sanitary lift station at Cariann Lane.

Friday, September 2, 2011

Next week, DiMeo Bros. is scheduled to continue work on the sanitary lift station at Cariann Lane. Also next week, DiMeo Bros. is looking to begin curb and gutter and sidewalk restoration on Cariann Lane and along East Lake Avenue from Cariann Lane to Sherwood Road.

Friday, August 26, 2011

Next week, DiMeo Bros. is scheduled to work on the sanitary lift station at Cariann Lane. Also next week, DiMeo Bros. is looking to begin curb and gutter and sidewalk restoration on Cariann Lane and along East Lake Avenue from Cariann Lane to Sherwood Road.

Friday, August 19, 2011

Next week, DiMeo Bros. will continue to work on the sanitary lift station at the southwest corner of Glenview Road and Arbor Lane. Also next week, DiMeo Bros. is scheduled to continue with utility work on Cariann Lane and along the south side of East Lake Avenue from Cariann Lane to Sherwood Road.

Friday, August 12, 2011

Next week, DiMeo Bros. will continue to work on the sanitary lift station at the southwest corner of Glenview Road and Arbor Lane. Also next week, DiMeo Bros. is scheduled to begin utility work on Cariann Lane.

Friday, August 5, 2011

Next week, DiMeo Bros. will continue to work on the sanitary lift station at the southwest corner of Glenview Road and Arbor Lane. Also next week, DiMeo Bros. is scheduled to begin work (clearing, sawcutting, erosion control installation, light pole relocation) in preparation for utility work on Cariann Lane.

Friday, July 29, 2011




Next week, DiMeo Bros. will continue to work on the sanitary lift station at the southwest corner of Glenview Road and Arbor Lane (see photos above).

Friday, July 22, 2011

Next week, the contractor is scheduled to work on the sanitary lift station at the southwest corner of Glenview Road and Arbor Lane. Late next week, the contractor may start utility work on Cariann Lane at Lake Street.

Friday, July 15, 2011

Next week, the contractor is scheduled to work on the sanitary lift station at the southwest corner of Glenview Road and Arbor Lane.

Friday, July 8, 2011

DiMeo Bros. looks to complete the installation of the sanitary force main across Glenview Road (west of Arbor Lane) this week. Next week, DiMeo Bros. will continue work on the sanitary lift station on Glenview Road, and install manholes and pipe west of Harms Road which will necessitate daily lane closures with flaggers.

Thursday, June 30, 2011

The contractor will continue working on the sanitary sewer installation (augering method) on the north side of Glenview Road crossing Harms Road (east to west) into next week.

Friday, June 24, 2011

DiMeo Bros. is scheduled to work on the sanitary sewer installation (augering method) on the north side of Glenview Road crossing Harms Road (east to west) next week. Please be alert to flaggers and construction signage as traffic patterns may change.

Thursday, June 16, 2011

DiMeo Bros. is scheduled to work on the sanitary sewer installation (augering method) on the north side of Glenview Road crossing Harms Road (east to west) next week. Please be alert to flaggers and construction signage as traffic patterns may change.

Friday, June 10, 2011

DiMeo Bros. is scheduled to work on the sanitary sewer installation (augering method) on the north side of Glenview Road crossing Harms Road (east to west) next week. Please be alert to flaggers and construction signage as traffic patterns may change.

Friday, June 3, 2011

DiMeo Bros. is scheduled to continue with the sanitary sewer installation on Glenview Road from Arbor Lane to Harms Road this week and into next week.

Friday, May 27, 2011


The contractor has finished the installation of the overflow sanitary
sewer pipe on Arbor Lane from Cunliff Park to Glenview Road using the
guided bore method. Next week they will be installing 2 deep manholes
across the intersection of Glenview Road and Arbor south of Glenview Rd.
Access in and out of Arbor will be limited. Residents may want to park
on Beaver during daytime hours. The contractor is scheduled to work on
the installation of the sanitary sewer on Glenview Road between Arbor
Lane and Harms Road.

The concrete contractor is scheduled to finish the curb and gutter
replacement on Arbor Lane from Glenview Road to Willmette Avenue this
week. Driveway access to these homes is scheduled to be restored next
week.

Monday, May 9, 2011

The contractor will have one crew working on the installation of the overflow sanitary sewer pipe on Arbor Lane from Cunliff Park to Glenview Road this week using a guided bore method. The guided bore method is used to minimize disturbance to the roadways, driveways and parkways.

The contractor will have a second crew which will start with replacement of water services on Arbor Lane from Glenview Road to Wilmette Avenue. There will be an occasion when the resident’s water service will be shut off for a few hours when the contractor is replacing the individual resident’s water service. The contractor will knock on doors before shutting off the resident’s water service.

Saturday, April 30, 2011

The contractor will have one crew continue with the installation of the overflow sanitary sewer pipe on Arbor Lane from Glenview Road to Wilmette Avenue into next week.

The contractor has added a second crew which will continue with the installation of the overflow sanitary sewer pipe through Cunliff Park and work northbound on Arbor Lane up to Glenview Road into next week.

Thursday, April 21, 2011

The contractor installed a deep manhole at the intersection of Glenview Road and Arbor Lane this week. The contractor will continue with the installation of the overflow sanitary sewer pipe on Arbor Lane from Glenview Road to Wilmette Avenue into next week. Additionally, mid-to-late next week the contractor will bring in a second crew to begin sanitary sewer installation in Cunliff Park. The sanitary sewer work in Cunliff Park begins approximately 300 feet south of Arbor Lane and continues north into the east parkway of Arbor Lane.

Friday, April 15, 2011

Dimeo Bros. has completed directional drilling the water main on Arbor Lane between Glenview Road and Wilmette Avenue.

The contractor for the construction work, DiMeo Brothers, has notified the Village of Glenview that they plan on starting the sanitary sewer installation on Arbor Lane from Glenview Road to Wilmette Avenue next week either Tuesday or Wednesday, weather permitting. This work will necessitate the closure of the intersection of Arbor Lane at Glenview Road and residents should access their homes via Wilmette Ave. The westbound lane of Glenview Road will be closed while working at the intersection and flaggers will be on site to allow two-way traffic on Glenview Road during working hours. Work at the intersection will take 2 to 3 days. From there they will continue north towards Wilmette Avenue. This sewer work will bring a lot of truck traffic to the street so please be cautious while driving. The contractor will also be posting no parking signs for daytime working hours.

The contractor is also scheduled to complete spot repairs to the sanitary sewer along Arbor Lane from Glenview Road to Wilmette Avenue next week.

Friday, April 8, 2011

Dimeo Bros. has completed directional drilling the water main on Arbor Lane between Glenview Road and Wilmette Avenue. DiMeo Bros. will now begin installing new fire hydrants and valves in vaults. Filling and flushing of the water main will be completed and then pressure testing and chlorinating. It is anticipated that water service connections to each home will commence the following week.

Friday, April 1, 2011

DiMeo Bros. has started directional drilling the water main on Arbor Lane between Glenview Road and Willmette Avenue. DiMeo Bros. will continue with the directional drilling of the water main on Arbor Lane between Glenview Road and Willmette Avenue for the next two weeks.

Monday, March 28, 2011

Construction will begin this week! The contractor has informed us that he will begin televising the inside of the sewer pipes, laying out where new construction will take place, and deliveries will also begin onsite. Additionally, water main installation will start this week.

Thursday, March 17, 2011

Construction to start soon.

A meeting was held last night (Wednesday, March 16) with the residents of the areas affected by construction.

The Contractor will begin surveying and construction layout on the project next week. The exact date of start has not been set at this time. However, the weather is getting nice outside and we expect the start date to be soon.

An update will be given closer to the start of construction.