Monday, November 21, 2011

Construction of this project is complete. All that remains is lift station start up procedures and punchlist.

Thursday, November 3, 2011

Next week, the contractor will be continuing punchlist work. Utility companies have completed their service connections to the lift stations and the contractor will be scheduling the lift station start up. Additionally, parkway restoration is scheduled to be completed around lift stations next week.

Friday, October 28, 2011

Next week, AT&T and Nicor will continue work on lift stations prior to the lift station start up. Also next week, the contractor will be installing asphalt surface course on Cariann Lane and will continue punch list repairs.

Wednesday, October 19, 2011

Starting next week, ComEd, AT&T and Nicor will be completing utility services to the lift stations prior to the lift station start up. Also next week, the contractor will be beginning punch list work.

Friday, October 14, 2011

Next week, the contractor will be beginning punchlist work. Additionally, ComEd, AT&T and Nicor will be completing utility services to the lift stations prior to the lift station start up within the next few weeks.

Wednesday, October 12, 2011

On the afternoon of October 12 the contractor will be coating the existing asphalt surface with fresh oil and sand on Arbor Lane. The oil will help the top coat of asphalt bond to the existing layer. The layer of sand is to help prevent tracking the oil into your driveways. Please try to keep your driving to a minimum while the oil dries. If you must drive on the oil, please drive slowly to help prevent splattering onto your vehicle.

Weathering permitting the contractor will then begin to pave the final layer of asphalt on Arbor Lane on Thursday, October 13.

Monday, October 10, 2011

UPDATE: Paving on Carriann Lane and Arbor Lane (between Glenview Road and Wilmette Avenue) is tentatively scheduled for Thursday of this week, weather permitting.

Friday, October 7, 2011

Next week, the contractor will be adjusting utility structures in preparation for asphalt paving on Carriann Lane and Arbor Lane (between Glenview Road and Wilmette Avenue). The contractor will also be working on parkway grading and restoration on Carriann Lane this week.

Friday, September 30, 2011

Next week, the electrical contractor is scheduled to continue wiring for the sanitary lift stations at Cariann Lane and Arbor Lane. On Cariann Lane, the concrete contractor is scheduled to begin installation of curb with the paving contractor scheduled to begin paving shortly after the curb installation.

Additionally, the paving contractor is scheduled to begin grinding the pavement on Arbor Lane in preparation for asphalt paving.

Friday, September 23, 2011

Next week, DiMeo Bros. is scheduled to continue piping within the sanitary lift station at Cariann Lane. Additionally, late next week the asphalt contractor will be grinding Arbor Lane from Glenview Road to Wilmette Avenue in preparation for asphalt resurfacing.

Friday, September 16, 2011

Next week, DiMeo Bros. is scheduled to continue work on the sanitary lift station at Cariann Lane.

Friday, September 9, 2011

Next week, DiMeo Bros. is scheduled to continue work on the sanitary lift station at Cariann Lane.

Friday, September 2, 2011

Next week, DiMeo Bros. is scheduled to continue work on the sanitary lift station at Cariann Lane. Also next week, DiMeo Bros. is looking to begin curb and gutter and sidewalk restoration on Cariann Lane and along East Lake Avenue from Cariann Lane to Sherwood Road.

Friday, August 26, 2011

Next week, DiMeo Bros. is scheduled to work on the sanitary lift station at Cariann Lane. Also next week, DiMeo Bros. is looking to begin curb and gutter and sidewalk restoration on Cariann Lane and along East Lake Avenue from Cariann Lane to Sherwood Road.

Friday, August 19, 2011

Next week, DiMeo Bros. will continue to work on the sanitary lift station at the southwest corner of Glenview Road and Arbor Lane. Also next week, DiMeo Bros. is scheduled to continue with utility work on Cariann Lane and along the south side of East Lake Avenue from Cariann Lane to Sherwood Road.

Friday, August 12, 2011

Next week, DiMeo Bros. will continue to work on the sanitary lift station at the southwest corner of Glenview Road and Arbor Lane. Also next week, DiMeo Bros. is scheduled to begin utility work on Cariann Lane.

Friday, August 5, 2011

Next week, DiMeo Bros. will continue to work on the sanitary lift station at the southwest corner of Glenview Road and Arbor Lane. Also next week, DiMeo Bros. is scheduled to begin work (clearing, sawcutting, erosion control installation, light pole relocation) in preparation for utility work on Cariann Lane.

Friday, July 29, 2011




Next week, DiMeo Bros. will continue to work on the sanitary lift station at the southwest corner of Glenview Road and Arbor Lane (see photos above).

Friday, July 22, 2011

Next week, the contractor is scheduled to work on the sanitary lift station at the southwest corner of Glenview Road and Arbor Lane. Late next week, the contractor may start utility work on Cariann Lane at Lake Street.

Friday, July 15, 2011

Next week, the contractor is scheduled to work on the sanitary lift station at the southwest corner of Glenview Road and Arbor Lane.