Wednesday, October 19, 2011
Friday, October 14, 2011
Wednesday, October 12, 2011
On the afternoon of October 12 the contractor will be coating the existing asphalt surface with fresh oil and sand on Arbor Lane. The oil will help the top coat of asphalt bond to the existing layer. The layer of sand is to help prevent tracking the oil into your driveways. Please try to keep your driving to a minimum while the oil dries. If you must drive on the oil, please drive slowly to help prevent splattering onto your vehicle.
Weathering permitting the contractor will then begin to pave the final layer of asphalt on Arbor Lane on Thursday, October 13.
Weathering permitting the contractor will then begin to pave the final layer of asphalt on Arbor Lane on Thursday, October 13.
Monday, October 10, 2011
Friday, October 7, 2011
Friday, September 30, 2011
Next week, the electrical contractor is scheduled to continue wiring for the sanitary lift stations at Cariann Lane and Arbor Lane. On Cariann Lane, the concrete contractor is scheduled to begin installation of curb with the paving contractor scheduled to begin paving shortly after the curb installation.
Additionally, the paving contractor is scheduled to begin grinding the pavement on Arbor Lane in preparation for asphalt paving.
Additionally, the paving contractor is scheduled to begin grinding the pavement on Arbor Lane in preparation for asphalt paving.