The contractor will have one crew working on the installation of the overflow sanitary sewer pipe on Arbor Lane from Cunliff Park to Glenview Road this week using a guided bore method. The guided bore method is used to minimize disturbance to the roadways, driveways and parkways.

The contractor will have a second crew which will start with replacement of water services on Arbor Lane from Glenview Road to Wilmette Avenue. There will be an occasion when the resident’s water service will be shut off for a few hours when the contractor is replacing the individual resident’s water service. The contractor will knock on doors before shutting off the resident’s water service.